PROJECT: Multi-Product Bulk Terminal
Engineering Methodology:
Feasibility study, complete project management including: engineering,
construction supervision, and startup assistance.
Construction Contracts: All contracts were lump sum, bid
at the same time. The project was completed within original budget,
31 months from start of feasibility study.
- Flat storage building
- Shiploader
- Ship unloader
- Traveling stackers
- Scraper-reclaimer
- Belt conveyor system
- Civil and marine works
Principal Features:
-
Covered bulk storage building 170 ft. wide by 1368 ft. long
with 14 compartments and expansion capability to 2,600 feet.
-
Portal scraper allowing 100% live storage and first in - first
out inventory control.
-
Luffing stackers inside building for dust-free storage to prevent
air pollution.
-
System flexibility permits handling 3 different materials at
the same time.
-
Vehicle loading and unloading stations can accommodate all
types of rail cars and trucks.
-
Dust control systems.
-
Quadrant type shiploader.
-
Handling rates:
- Rail and truck unloading at 1200 TPH.
- Rail and truck loading at 1400 TPH.
- Barge and ship loading at 1400 TPH.