PROJECT: New Material Handling Facility
Principal Features:
-
Facility designed for a throughput capacity of 3000 tph iron
ore, 1700 tph coal and 1100 tph DRI.
-
Storage yard can accommodate up to 1,000,000 tons of coal
and 720,000 tons of iron ore.
-
Vessels up to Cape size can be loaded or unloaded at a rate
of up to 3,000 tph.
-
Railcar loadout system contains state of the art batch weighing.
-
3000 tph slewing, luffing traveling stacker can stockpile
either coal or iron ore.
-
Two 1000 tph portable conveyors are used to reclaim iron ore
from the stockpile and feed it to the DRI plant.